Aspen Pharma
Custom House Quay, Dublin 2

Design and Build project from initial space planning for Lease negotiation, to Landlord consent phase, through to detailed design, costing, planning, constructing and overall hand-back. The complete project life cycle, managed from start-to-finish by Sonica.

Open plan spaces were developed off the Client’s international office templates, with the expressed requirement to improve existing flow and promote productivity. Our designers took the starting point from a Dubai based plan and streamlined it into an improved Dublin model to achieve these goals.

Works were undertaken inside a 12-storey multi tenanted building. Management of logistics and daily co-ordination with the sitting Building Management Team was a key consideration in the development of our aggressive construction programme which was led by Client early occupational requirements.

A high degree of cellularisation in the offices required considerable addition to the Landlord provided A/C and lighting control systems. These A/C & lighting upgrades were carried out to provide local dedicated user defined control and were simultaneously linked back to the head end BMS system for Landlord energy monitoring.

The project was run as an open book Management Contract, with the Client retaining all expenditure authorization throughout the build process. The completed works were delivered below the original approved budget tabled at Design completion stage.

From initial meeting to final handback, we knew that in Sonica Fitout we had a Design & Build Contractor that could translate the multi-faceted requirements of our business needs into a single, co-ordinated and stream lined project action plan. They listened, they advised and they delivered a space that has gone way beyoned all of our expectations.

Elisha O'Keeffe, Aspen Pharma Ireland

Size

  • 750m2

Timescale

  • 8 weeks on site

Features

  • International collaboration at design phase to achieve Client design goals.
  • Open plan financials with project delivered on time and below budget.
  • Comms room commissioned and complete 3 weeks before handover to allow Client IT access.
  • Client direct vendors were managed into our overall programme to ensure complete co-ordination of overall project completion.

Size

  • 750m2

Timescale

  • 8 weeks on site

Features

  • International collaboration at design phase to achieve Client design goals.
  • Open plan financials with project delivered on time and below budget.
  • Comms room commissioned and complete 3 weeks before handover to allow Client IT access.
  • Client direct vendors were managed into our overall programme to ensure complete co-ordination of overall project completion.