United Drug Group
Citywest Business Campus

Designed by RKD Interiors, our brief took the assignment from an Existing Landlord CAT-A area over 2-separate tenancies, both of which were then fully stripped back to basic shell and core structure as part of our works, to become UDG Healthcare’s Corporate HQ within a 10-week period from Commencement on site.

Works were performed unobtrusively within a fully engaged, highly trafficked, multi-tenanted building with close overlap to Campus Management, Client Stakeholders and neighbouring tenants.

Packages encompassed a sizeable stylish joinery element and complex Mechanical, Electrical & IT upgrades to service the open-plan work-space areas and segmental modular offices & meeting rooms. The main Reception features an inviting design element luring to a quirky ‘Breakout Area Canteen’ with feature brick internal facades, critall glazed screens, floating ‘wooden’ acoustic ceilings and matchless tiled flooring.

Due to the nature and scale of the sharp trapezoidal shaped walls and ceilings, paired with the diverging display of flooring and wall colours, the detailing in the Architectural packages required a Sonica level of attention to guarantee that the Architects vision for the completed space was realised.

It was great to work with Hugh Ward and his team at Sonica Fitout on our new HQ in Riverwalk, Citywest. We were very impressed with the level of professionalism and attention to detail on every aspect of this project which produced a high standard of finish. Sonica Fitouts commitment to this project ensured that it came in on programme and within budget. Everyone is delighted with the final result.

Donal Burke, Head of Procurement

Size

  • 1,250m2

Timescale

  • 1-week Pre-Con
  • 10 weeks on site

Features

  • Design and VE development to suit strict budget parameters
  • Comms room commissioned and complete 3 weeks before handover to allow Client IT access
  • Liaison and management of Client Direct vendors
  • Project acceleration to ensure no client ‘down-time’ and smooth, quick turn-around on staff migrations
  • Co-ordination with local Team on relocation deliverables
  • M&E and IT upgrades throughout
  • Turnkey furniture package

Size

  • 1,250m2

Timescale

  • 1-week Pre-Con
  • 10 weeks on site

Features

  • Design and VE development to suit strict budget parameters
  • Comms room commissioned and complete 3 weeks before handover to allow Client IT access
  • Liaison and management of Client Direct vendors
  • Project acceleration to ensure no client ‘down-time’ and smooth, quick turn-around on staff migrations
  • Co-ordination with local Team on relocation deliverables
  • M&E and IT upgrades throughout
  • Turnkey furniture package